Terms & Conditions 2007

On receiving instructions to commence the project from you, we will order the goods required from our suppliers. Our suppliers will confirm to us the supply date of your kitchen/bathroom/bedroom furniture accordingly. We will then contact you to arrange an installation starting date. Under normal circumstances, your installation will begin the following week upon delivery of the goods ordered. Our normal times of work are start at 8.30am and finish at 4.30/5.00pm daily. Other times will be with your agreement.

 

We reserve the right to change the following terms and conditions without notice. The following statements do not affect your statutory rights.

 

1. All costs are exclusive of VAT, currently at the rate of 17.5%.

2. Anything that is not listed in the contract schedule - will not be included in the project.

3. The removal of all waste material, created by the installation, is the customer's responsibility to dispose of, unless otherwise agreed and priced.

4. The customer should ensure that all drawings and design schedule represent the project accurately to allow us to complete the installation to your satisfaction.

5. The project may be a big investment by youselves - please take time to satisfy yourselves that the specifications represent what you want. If you are unsure, we will be only too pleased to offer further advice, and where necessary we will make a further appointment to visit you, to ensure we reach mutual agreement accordingly. We would rather do this than find our customer not satisfied on practical completion.

6. In general terms the cost for the installation includes

a. Installation of all units, worktops, butt & scribe jointing, cornices, pelmets and plinths (where applicable)

b. Hot & cold water services for sinks and appliances (where applicable)

c. Gas work to serve cooking appliances (where applicable)

d. Connection of appliances to 'suitable' power outlets i.e. a ring main within close proximity of the appliance (no extensions.to the appliance cord will be considered)

7. Payment terms if you wish to proceed are NO DEPOSIT, but 50% of the project balance on day one, with the delivery of your.goods ready for installation and the remainder of the balance on practical completion.

8. If there is damage that requires replacement, which runs over practical completion, then a retention of an agreed sum will be taken out of the balance owed (in normal circumstances this will be 5-10% of the outstanding balance, depending on the quantity of remedial work required).

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Dezines Internet Solutions Limited © 2001 - 2007. All Rights Reserved